The Combined Sewer Overflow (CSO) at the Wastewater Treatment Plant (#602) began to discharge on 6/5/2019 at 1828 hours and stopped at 2140 hours. 0.02 MGD were discharged into the Turkeyfoot Creek. No public access areas were impacted.

(UPDATE) The CSO (#602) at The Wastewater Treatment Plant, NPDES permit number 2PD00016, began to discharge into the Turkeyfoot creek on 6/2/2019 at 1250 am. The discharge stopped 6/3/2019 at 1603 hours. 4.80 MGD was released into Turkeyfoot creek. No public access areas were impacted. For information on CSO's and their locations in the city, please click on departments, scroll to wastewater plant and go to the bottom of the page. Questions can be answered by calling the Wastewater plant at 419-335 3026 during regular busniess hours. Monday-Friday, 8:00-4:00.